Melbourne Water M102 Pipeline Upgrade

 
Name: M102 Water main upgrade – North Essendon to Footscray watermain renewal

Client: Water Resources Alliance (WRA)

Completed: September 2012

Project outcome:
This significant Melbourne Water Corporation asset required an upgrade to meet the current and future needs of this growing population.  This complex project required open cut lift and relay pipeline renewal of Ø1200 OD MSCL in difficult greasy back ground conditions.   Project scope included traffic management, excavation, lay, backfill and reinstatement. Works included crossing Ballarat Road utilizing slip lining of the existing 1200 MS pipe with new Ø960 OD MSCL pipe and the 24/7 crossing of the signalised intersection at Churchill Avenue.

WRA Logo

pj-1-water-main-upgrade
pj-1-watermain-renewal