M102 North Essendon to Footscray Watermain Renewal

Name:M102 North Essendon to Footscray Watermain Renewal

Client: Water Resources Alliance (Baulderstone, UGL & Melbourne Water) – Ashley St Stage 1

John Holland KBR JV (for Melbourne Water) – Avondale heights and Ashley Street Stage 2

Construction Duration: Stage 1 – March to October 2012, Stage 2 – May 2015 to October 2017

Project Scope:
Stage 1 (2012) – Open cut and lift & relay pipeline renewal of Ø1200 OD MSCL pipe in the South bound Lanes of Ashley Street Maidstone in difficult greasy back ground conditions. Scope included Traffic Management, Excavate, Lay, Backfill and Reinstatement. Works included crossing Ballarat Road utilising slip lining of the existing 1200 MS pipe with new Ø960 OD MSCL pipe and the 24/7 crossing of the signalised intersection at Churchill Avenue.

Stage 2 (2015) – Open cut and lift & relay pipeline renewal of Ø1200 OD MSCL pipe through residential pipe track in Avondale Heights, through Medway Golf Club and in the South bound Lanes of Ashley Street in Braybrook.

Stage 1

Stage 2